Note: Some options and features may vary from the article below based on your CS Project package.
CS Project allows you to show the progress tracking line on tasks that have been completed ahead of schedule.
To show this progress tracking line – Follow these steps
1.) Go to the start menu and click on ‘Preferences’.
2.) Go to the ‘Other’ tab and tick the box ‘Progress line must inc…’ and press OK.
Enabling the Progress Line
1.) You must now enable the Progress line. To do this, go to the Configuration tab and click ‘Bar Chart Options’, or right click on the bar chart and select ‘Bar Chart Options’.
2.) Make sure the box at the bottom says ‘Advanced’, then tick the box ‘Progress (current) and press OK.
The progress line will now be displayed on the bar chart and will include activities ahead of schedule.